Tower Crane Dismantling Method: Statement

Tower Crane Dismantling Method Statement is a high-level safety document that details the specific sequence, equipment, and precautions required to safely decommission a tower crane. Because dismantling is a high-risk operation involving heavy loads at height, strict adherence to a pre-approved sequence is critical to maintain structural balance. 1. Pre-Dismantling Preparation

5. Permits and notifications

  • Obtain permit to work, lifting permit, hot works permit (if needed), confined space permit (if needed).
  • Notify local authorities/traffic management if road closures or oversized loads are required.
  • Notify personnel, site neighbours and stakeholders of planned activities and exclusion zones.
  • Inventory of all components (match against manufacturer’s parts list).
  • Inspection for damage (cracks, bent flanges, missing pins).
  • Cleaning and packing of bolts and small parts into labeled crates.
  • Sign-off by Appointed Person and Site Manager.
  • Update of site traffic plan – removal of exclusion zones.

The slewing ring and cab are typically removed as one unit before the final mast sections. Phase 6: Base & Foundation The fixing angles or foundation anchors are released. The remaining base section is removed. tower crane dismantling method statement

Step 1: Remove Wind Vane & Electrical Disconnect

  • Turn off main power at distribution box.
  • Lock out / tag out (LOTO) the isolator.
  • Remove the wind vane (anemometer assembly) and stow safely.