Tower Crane Dismantling Method: Statement
Tower Crane Dismantling Method Statement is a high-level safety document that details the specific sequence, equipment, and precautions required to safely decommission a tower crane. Because dismantling is a high-risk operation involving heavy loads at height, strict adherence to a pre-approved sequence is critical to maintain structural balance. 1. Pre-Dismantling Preparation
5. Permits and notifications
- Obtain permit to work, lifting permit, hot works permit (if needed), confined space permit (if needed).
- Notify local authorities/traffic management if road closures or oversized loads are required.
- Notify personnel, site neighbours and stakeholders of planned activities and exclusion zones.
- Inventory of all components (match against manufacturer’s parts list).
- Inspection for damage (cracks, bent flanges, missing pins).
- Cleaning and packing of bolts and small parts into labeled crates.
- Sign-off by Appointed Person and Site Manager.
- Update of site traffic plan – removal of exclusion zones.
The slewing ring and cab are typically removed as one unit before the final mast sections. Phase 6: Base & Foundation The fixing angles or foundation anchors are released. The remaining base section is removed. tower crane dismantling method statement
Step 1: Remove Wind Vane & Electrical Disconnect
- Turn off main power at distribution box.
- Lock out / tag out (LOTO) the isolator.
- Remove the wind vane (anemometer assembly) and stow safely.